Examples and Use Cases
The values below are sample numbers to show how the columns work.
Example 1: Building a Revenue SOV from the owner's bid sheet
Your signed owner contract is $250,000.00. The bid sheet is in Excel. You copy these rows and click Paste New Rows in the Default group:
| Pay item No. | Owner pay item | Description | Unit | Unit cost | Quantity | Contract estimated |
|---|---|---|---|---|---|---|
| 001 | 20200100 | Earth excavation | CY | $40.00 | 2,500 | $100,000.00 |
| 002 | 20800150 | Trench backfill | CY | $75.00 | 1,200 | $90,000.00 |
| 003 | 30100000 | Mobilization | Lump Sum | $55,500.00 | 1 | $55,500.00 |
The TOTAL row shows a warning: "Contract Estimated total doesn't match Contract value ($250,000.00) DIFF: -$4,500.00". You find a missing line, add it with Add New Row (Traffic control, LS, $4,500.00), and the message turns green. You click Save Changes.
Example 2: Billing a month of work
In March, the crew excavated 600 CY and mobilization is half done.
- Row 001: enter 600 in Current pay estimate QTY. The amount fills in as $24,000.00 (600 × $40.00). JTD vs Contract shows 24%.
- Row 003 (lump sum): enter 50% in Current pay estimate. The amount fills in as $27,750.00. You save, click Generate pay app, set Period to = March 31, choose Draft to review with the owner first, and generate. With 10% summary retainage, the Summary shows $5,175.00 retainage on $51,750.00 completed.
Example 3: Tracking a subcontractor by phase
You manage an electrical subcontractor with 40 line items. On Subcontracts SOV, you select the vendor and create groups Level 1, Level 2 and Roof. You move each row into its group. Each group now shows its own GROUP SUBTOTAL, so you can see how far each floor is billed.
Example 4: Reviewing the forecast
Before a monthly cost review, the project manager turns on Forecasting view. The table shows only the contract, current contract, job-to-date and CTC Projected Total columns. They update the projected quantity on rows that will run over. Projected vs Contract shows the expected gain or loss per row, in green or red.
Example 5: A change order is approved
The owner approves a change order adding 300 CY of excavation at $40.00. Row 001 now shows $12,000.00 in New changes, and Current contract rises to $112,000.00. Clicking the New changes amount opens the list of change orders behind it.